Two days ago, the Fort Collins city council gave second reading to Ordinance No. 102, waiving basic development review and associated land-use standards to facilitate Larimer County-led plugging and abandonment of orphaned wells in the city's northeast. The first reading passed unanimously on July 21; the second confirms it. A municipal land-use waiver will never trend nationally. It should — because local permitting is the hidden schedule driver in orphan-well timelines everywhere.
The months nobody budgets
Follow a typical orphan well's calendar and find the local-permit gap. The state program ranks the well, packages it, bids it, awards it — and then the contractor discovers the site sits inside a city limit, a county development zone, or a special district whose approvals were never sequenced into the schedule. Development review, grading permits, noise variances for round-the-clock work, road-use agreements for heavy mobilization: each takes weeks, they run sequentially more often than concurrently, and none appears in the state program's timeline because none belongs to the state program.
Fort Collins just deleted its share of that gap for Larimer County's P&A work. The ordinance waives the review requirements that would otherwise apply to plugging operations — not environmental standards, not safety rules, but the procedural layers that add calendar without adding protection. Plugging a leaking well is remediation, not development; reviewing it as if it were a shopping center was always category error. The council's unanimous votes say the category error is now fixed.
Why cities usually do the opposite
The usual municipal posture toward oilfield work is restriction, and usually for good reason: residents near production bear noise, traffic, and risk, and local review is their leverage. But orphan wells invert the equities. The operator is gone; the choice is not between drilling and quiet but between plugging and leaking. Every month of review delay is a month of methane migration, groundwater exposure, and documented hazard — imposed on the same residents the review process exists to protect.
Cities that grasp the inversion move fast; cities that apply the production-era playbook to orphan work stall their own remediation. The difference is usually one informed staffer or one councilmember who has walked an orphan site. Fort Collins had them. Most cities have not found them yet — which is why state programs should brief municipal officials as a standard step in package assembly, not as damage control after the schedule slips.
The Larimer County pipeline
The ordinance facilitates county-led P&A, which points at the delivery model underneath: Larimer County running plugging work with municipal cooperation, presumably against state or federal funding. County-led execution has real virtues — local inspectors, local relationships, short paths from decision to rig — and one structural weakness: counties depend on every overlapping jurisdiction clearing the path. Fort Collins clearing its segment converts the county's schedule from hopeful to plannable.
Watch the northeast Fort Collins sites as a natural experiment. Same wells, same county program, same funding — with the municipal friction removed. If those plugs complete materially faster than comparable sites still navigating full review elsewhere, the result quantifies what every field hand already knows: the calendar is made of permits.
What this means beyond Colorado
Every state with urban-adjacent orphan wells — which is to say, nearly every producing state — has a Fort Collins opportunity sitting in its backlog. The playbook: inventory which ready packages touch municipal process, brief the relevant councils with the inversion argument (plugging is remediation, delay is exposure), and propose targeted waivers modeled on this ordinance. Unanimous votes follow understanding; understanding follows one good briefing.
For contractors, municipal posture is now a bid input worth tracking. Packages in cooperative jurisdictions carry less schedule risk and fewer standby days; packages in unbriefed ones carry both. Our access flags already capture seasonal and road constraints — municipal cooperation belongs in the same triage, and bidders who track it will price more accurately than bidders who discover it at mobilization.
What we think at Terrabillion
The fastest plug is the one nobody delays. Fort Collins understood that reviewing remediation as development serves neither rigor nor residents, and acted unanimously — twice. State programs assemble packages; counties execute them; but cities like this one decide whether the calendar measures weeks or seasons. Every other municipality sitting on orphan wells should read Ordinance 102 and ask why its own review process treats plugging crews like developers. The wells leak while the paperwork sits. Clear the path.
More blog posts to read

Pennsylvania plugs its 500th well and funds the science behind the next 500
The 500th plug under Governor Shapiro, $215M in IIJA grants behind it, and a $2.4M health study ahead. Pennsylvania week in review.

A nonprofit just saved taxpayers $2.25M plugging Pennsylvania wells
The Well Done Foundation's 15th Pennsylvania plug, a $2.25M taxpayer value — and proof the third funding lane works.