SOH-1/SOH-2 geothermal observation wells: 1991 research history and Dec 2016 P&A schedule
- Record
p09-HI-rec-02- State
- HI
- Category
- wells · well_background_schedule
- Status
- collected
- Period
- current
- Quality
- Unreviewed
- Review state
- Pending review
- Native ID
HI-DLNR-SOH1-SOH2-WELLS
Fields
- drilled
- Drilled in 1991 for research purposes
- duration
- The project is expected to be completed in approximately 3 months.
- meeting
- Thursday, December 8, from, 6-8 p.m. at Pahoa Community Center
- monitoring end
- for geothermal resource monitoring purposes
- purpose
- to monitor temperature gradients down the shafts
- reuse status
- are no longer being used by the University of
- schedule
- by about December 12 work will begin on plugging the well and restoring the area with SOH-2 to follow in a similar manner
- work hours
- Work hours will be limited to between 7 a.m. to 7 p.m. daily.
Evidence
- drilled:
Drilled in 1991 for research purposes
https://dlnr.hawaii.gov/blog/2016/11/25/nr16-245/ · release body, history paragraph (verbatim in evidence/p09-HI-extracts.txt) · sourcep09-HI-src-01· visitp09-HI-visit-01 - purpose:
to monitor temperature gradients down the shafts
https://dlnr.hawaii.gov/blog/2016/11/25/nr16-245/ · release body, history paragraph (verbatim in evidence/p09-HI-extracts.txt) · sourcep09-HI-src-01· visitp09-HI-visit-01 - reuse status:
are no longer being used by the University of
https://dlnr.hawaii.gov/blog/2016/11/25/nr16-245/ · release body, history paragraph (verbatim in evidence/p09-HI-extracts.txt) · sourcep09-HI-src-01· visitp09-HI-visit-01 - monitoring end:
for geothermal resource monitoring purposes
https://dlnr.hawaii.gov/blog/2016/11/25/nr16-245/ · release body, history paragraph (verbatim in evidence/p09-HI-extracts.txt) · sourcep09-HI-src-01· visitp09-HI-visit-01 - meeting:
Thursday, December 8, from, 6-8 p.m. at Pahoa Community Center
https://dlnr.hawaii.gov/blog/2016/11/25/nr16-245/ · release body, meeting paragraph (verbatim in evidence/p09-HI-extracts.txt) · sourcep09-HI-src-01· visitp09-HI-visit-01 - schedule:
by about December 12 work will begin on plugging the well and restoring the area with SOH-2 to follow in a similar manner
https://dlnr.hawaii.gov/blog/2016/11/25/nr16-245/ · release body, schedule paragraph (verbatim in evidence/p09-HI-extracts.txt) · sourcep09-HI-src-01· visitp09-HI-visit-01 - duration:
The project is expected to be completed in approximately 3 months.
https://dlnr.hawaii.gov/blog/2016/11/25/nr16-245/ · release body, schedule paragraph (verbatim in evidence/p09-HI-extracts.txt) · sourcep09-HI-src-01· visitp09-HI-visit-01 - work hours:
Work hours will be limited to between 7 a.m. to 7 p.m. daily.
https://dlnr.hawaii.gov/blog/2016/11/25/nr16-245/ · release body, schedule paragraph (verbatim in evidence/p09-HI-extracts.txt) · sourcep09-HI-src-01· visitp09-HI-visit-01
Provenance
Collected 2026-10-05 by agent p09-HI. Still missing: well depths, api numbers, completion status.