SOH-1/SOH-2 geothermal observation wells: 1991 research history and Dec 2016 P&A schedule

Record
p09-HI-rec-02
State
HI
Category
wells · well_background_schedule
Status
collected
Period
current
Quality
Unreviewed
Review state
Pending review
Native ID
HI-DLNR-SOH1-SOH2-WELLS

Fields

drilled
Drilled in 1991 for research purposes
duration
The project is expected to be completed in approximately 3 months.
meeting
Thursday, December 8, from, 6-8 p.m. at Pahoa Community Center
monitoring end
for geothermal resource monitoring purposes
purpose
to monitor temperature gradients down the shafts
reuse status
are no longer being used by the University of
schedule
by about December 12 work will begin on plugging the well and restoring the area with SOH-2 to follow in a similar manner
work hours
Work hours will be limited to between 7 a.m. to 7 p.m. daily.

Evidence

  1. drilled: Drilled in 1991 for research purposes
    https://dlnr.hawaii.gov/blog/2016/11/25/nr16-245/ · release body, history paragraph (verbatim in evidence/p09-HI-extracts.txt) · source p09-HI-src-01 · visit p09-HI-visit-01
  2. purpose: to monitor temperature gradients down the shafts
    https://dlnr.hawaii.gov/blog/2016/11/25/nr16-245/ · release body, history paragraph (verbatim in evidence/p09-HI-extracts.txt) · source p09-HI-src-01 · visit p09-HI-visit-01
  3. reuse status: are no longer being used by the University of
    https://dlnr.hawaii.gov/blog/2016/11/25/nr16-245/ · release body, history paragraph (verbatim in evidence/p09-HI-extracts.txt) · source p09-HI-src-01 · visit p09-HI-visit-01
  4. monitoring end: for geothermal resource monitoring purposes
    https://dlnr.hawaii.gov/blog/2016/11/25/nr16-245/ · release body, history paragraph (verbatim in evidence/p09-HI-extracts.txt) · source p09-HI-src-01 · visit p09-HI-visit-01
  5. meeting: Thursday, December 8, from, 6-8 p.m. at Pahoa Community Center
    https://dlnr.hawaii.gov/blog/2016/11/25/nr16-245/ · release body, meeting paragraph (verbatim in evidence/p09-HI-extracts.txt) · source p09-HI-src-01 · visit p09-HI-visit-01
  6. schedule: by about December 12 work will begin on plugging the well and restoring the area with SOH-2 to follow in a similar manner
    https://dlnr.hawaii.gov/blog/2016/11/25/nr16-245/ · release body, schedule paragraph (verbatim in evidence/p09-HI-extracts.txt) · source p09-HI-src-01 · visit p09-HI-visit-01
  7. duration: The project is expected to be completed in approximately 3 months.
    https://dlnr.hawaii.gov/blog/2016/11/25/nr16-245/ · release body, schedule paragraph (verbatim in evidence/p09-HI-extracts.txt) · source p09-HI-src-01 · visit p09-HI-visit-01
  8. work hours: Work hours will be limited to between 7 a.m. to 7 p.m. daily.
    https://dlnr.hawaii.gov/blog/2016/11/25/nr16-245/ · release body, schedule paragraph (verbatim in evidence/p09-HI-extracts.txt) · source p09-HI-src-01 · visit p09-HI-visit-01

Provenance

Collected 2026-10-05 by agent p09-HI. Still missing: well depths, api numbers, completion status.